Minimum self-cleansing velocities are based on empirical research and experience. The values used for design purposes are based on typical sediment loads expected in normal conditions. However, caution should be taken to ensure that the anticipated sediment load and the composition the material carried in the flow is within normal expectations for foul and surface water wastewater systems. If excessive sediment loading is anticipated it is best practice (even in "normal" situations) to incorporate an effective means of sediment control at the head of the flow, e.g. with a gully, silt trap or hydrodynamic separator.
Remember, the larger the pipe and the flatter the gradient, the greater the flow rate required to achieve self-cleansing velocity. It is unwise to select too large a pipe "to allow for possible development" as this may lead to settling out of solids, long retention periods, blockages and build-up of septicity. For in-line surface water attenuation systems, this can sometimes be overcome with "low flow" channels built into the invert of the larger pipe or box culvert.
It should also be remembered that self-cleansing velocities may only be achieved periodically and accumulation of detritus can occur within the system at lower flows until the higher flow "design" events take place. In these situations, the accumulated material may not be flushed through the system when self-cleansing velocities occur and over time the sewer may become blocked. Regular inspection and maintenance of sewers is therefore critical to ensure their optimum performance. The minimum design self-cleansing velocities recommended in Sewers for Adoption are:
Foul sewers: 0.75m/sec at one third design flow.
Surface water sewers: 1.0m/sec at full pipe flow.